Skip to priority announcement. Skip to main content

Power Electrics is Proudly Employee Owned

3.5MVA for Renewable Water Source Heat Pump Facility

Power Electrics was contacted when one of the largest renewable water source heat pump facilities in Europe needed temporary power until its new high voltage (HV) mains supply was installed.

The Challenge

The distribution network operator (DNO), who oversees the power lines and infrastructure of the heat pump facility were being delayed by land ownership issues. This in turn affected the route of the new HV supply to the facility. This meant Power Electrics were tasked, working alongside the equipment supplier, in providing the loads required to keep the facility fully functioning.

This involved comprehending any fluctuation in loads, requiring different forms of equipment during the build and commissioning process. There was also the problem of tight access into the facility and the adverse ground conditions.

500kVA generators in the snow

The Solution

Working alongside the equipment supplier the facility required a substantial 2800kW, equivalent to 3500MVA, load. A plan was developed where multiple 500kVA generators would be used, instead of larger sets, due to very tight site access, difficult ground conditions and fluctuating load requirements. Power Electrics provided fuel management throughout the project along with 7 x 500 kVA synched generators, 7 x 3000 Litre fuel tanks, 5000 Amp common bus isolator and over 1500m of cabling.

Multi-Megawatt Hire Multi-Megawatt Hire

Rental Projects Manager, Rob Mason, said: “The biggest challenge for this site was balancing suitably large sets for the loads and impacts against a very remote and challenging access route. As always our in-house transport team turned up trumps and provided the best solution for the challenge.”

 

Transport Fleet Transport Fleet

"As always our in-house transport team turned up trumps and provided the best solution for the challenge."
Rental Projects Manager, Rob Mason

As a result, the water source heat pump facility was able to continue operating while it awaited a permanent HV power supply.